Weekly Construction Update: 9/28/2011
This week demolition of north plaza is ongoing.
Next week, the following work is expected:
Next week, the following work is expected:
- Continuation of north plaza demo
- Demolition of portions of the vesting sacristy
- Removal of waterproofing along the north side
- Concrete work
Wednesday, September 21, 2011
Weekly Construction Update: 9/21/2011
This week the following work is expected or has already taken place:
- Orient lobby for primary entrance via the south plaza
- Install temporary fencing around north plaza to establish construction zone
- Demolish the north side store front including overhang
- Removal of trees in north plaza garden
- Complete storefront demo
- Begin demolition of north plaza, including break-up and removal of concrete.
Thursday, September 15, 2011
Construction Progress Week Of 9/12/2011
When entering via the south plaza, expect to see this open cavity in the overhang. It will be closed later in construction. It is secure for walking under.
Completed ramp. Railings to be installed.
Arial view of south plaza.
The sunken rectangular cavity in the wall will be a planter.
Limestone wall and granite cap installed at south plaza Rush Street entrance.
Installing granite caps on Rush Street wall.
Rush Street property wall.
Weekly Construction Update: 9/15/2011
This week the following work is expected:
- Complete handrail installation on south plaza stairs and ramps
- Complete final clean-up of the south plaza
- Relocate the temporary wall currently behind reception to the north side storefront area
- Finish prepping the lobby for primary entrance via the south plaza
- Install temporary fencing around north plaza to establish construction zone
- Demolish the north side store front including overhang
Thursday, September 8, 2011
Weekly Construction Update: 9/8/2011
This week, the following work is expected:
· Complete stair installation on west side of south plaza
· Complete granite cap installation on south plaza east/west wall
· Partial removal of scaffolding required for granite cap installation
· Install south storefront glass
· Install east stairs on south plaza
· Install handrails on south plaza stairways and ramps
· Install remaining miscellaneous pavers on south plaza
· Install limestone on south plaza north/south walls
· Delivery of granite caps for south plaza north/south walls
Next week, contractors will:
· Finish removing the scaffolding structure on the south plaza
· Complete handrail installation
· Finish installing the granite caps on the south plaza north/south wall
· Complete final clean-up of the south plaza
· Relocate the temporary wall currently behind reception to the north side
· Prep the lobby for primary entrance via the south plaza
Construction is now targeted to transition to the north plaza on or about 9/19/2011. Temporary directional signage will be posted when the north plaza is enclosed by fencing to secure the construction zone.