Wednesday, October 26, 2011

Construction Progress Week of 10/24/2011

demolition of roof over vesting sacristy

 North plaza demo and excavation

 More vesting sacristy room demo

Weekly Construction Update: 10/26/2011

This week the following work is expected to take place:
  • demolition of the roof of the vesting sacristy
  • demo and excavation of the North plaza
  • cutting walls on the lower level
  • competion of asbestos removal on the lower level
  • installation of ceiling on external building overhang.
Next week the following work is expected:
  • demolition of concrete on the lower level
  • work on the underpining for the new elevator
  • installation of storefront steel on the north plaza
  • installation of storefront glass on the north plaza

Wednesday, October 19, 2011

Weekly Construction Update: 10/19/2011

This week the following work is expected to take place:
  • Removal of asbestos from the lower level
  • Demo and excavation at and up to the north wall of the building
  • External demolition at the location of the vesting sacristy
All of these projects will continue into the following week (10/24 - 10/28)

Wednesday, October 5, 2011

Construction Progress Week of 10/3/2011

Demolition of the north plaza


Weekly Construction Update: 10/5/2011

This week, the following work has or is expected to take place:
  • continuing plaza demo
  • soft (minimal vibrations) interior demolition of the vesting sacristy, including mechanical, electrical, and plumbing
  • removal of waterproofing on the north plaza/lower level of building
  • concrete framing on the north plaza
Next week, the following work is expected:
  • continuation of vesting sacristy demo
  • continuation of concrete framing
  • storefront steel work on north plaza lower level
  • asbestos abatement of some pipes