This week the following work was expected/completed:
Installation of base plates for steel installation in link footprint
Building southeast wall of link
Crane arrives and begins work
Begin erecting steel and installing decking in the link area
Pouring concrete in stairs and ramp on north plaza
Continued work on ceiling and framing in the lower level, including electrical work
Building shaft wall around office building elevator pit
Remaining demo in the sacristy area of the link
Installing shoring, base plates, bar joists, and a core for a new column in the sacristy area of the link
Installation of piping in the restrooms east of the restroom riser column.
Next week the following work is expected:
Continue to erect steel in the footprint of the future link
Remove the old ramp from the lower level and begin framing for a new ramp
Continued work on ceiling and framing in the lower level, including electrical work
Building cinder block walls to enclose the new pump room in the lower level
Finishing up riser piping in office building restrooms and repairing areas affected by the work.