Friday, January 27, 2012

Construction Progress in Pictures - Week of 1/23/2012

Cooling tower gone

Cooling tower gone

65 E Huron office building elevator pit

Temporary shoring

Link elevator pit poured

Link elevator pit poured

New steel and temporary shoring

New steel

Base of new column

Demo of kitchen plumbing

New steel in mechanical room

Trenching

Wednesday, January 25, 2012

Weekly Construction Update: 1/25/2012

This week the following work is expected:
  • Excavation, waterproofing, framing and rebar of 65 E Huron building elevator pit
  • Column and steel install in the southwest corner of the lower level
  • Begin layout of underground plumbing in the lower level
  • Cooling tower demo in the alley/loading dock area
  • Installation of structural steel in the alley/loading dock area
Next week the following work is expected:
  • Pouring concrete into prepared floor of 65 E Huron building elevator pit
  • Framing and pouring elevator pit walls (lower level)
  • Continued excavation in the lower level (expect noise)
  • Building temporary wall in the lower level in the loading dock area (southwest corner of lower level)