Wednesday, May 25, 2011

Weekly Construction Update: 5/25/2011

The layout of the granite pavers has been approved. (See photo below.) Minor modifications are being implemented to move forward, weather permitting.

Due to the rain this week, the removal of the existing waterproofing has been delayed until after Memorial Day.  

Beginning on May 31, the contractor will demolish and remove the waterproofing, core and install a new drain and begin the framing for the concrete.