In the coming week, Pepper Construction anticipates the following work:
· Demo the existing waterproofing, weather permitting, Monday through Thursday
· Install new storefront steel and new waterproofing Tuesday through Friday
If the demo of the existing waterproofing creates extreme noise conditions in the lobby, it will be closed during that work. The offices, however, will remain open. We will assess the noise level on Monday and notify the building if lobby closure will be necessary.
The following week, Pepper Construction plans to:
· Begin framing for the concrete layout
· Demo the south lobby plaster ceiling (behind the temporary partition wall)
· Continue installation of upper storefront steel
No comments:
Post a Comment