Wednesday, July 27, 2011
Weekly Construction Update: 7/27/2011
The pavers have been delivered! The dumpster on Rush Street has been relocated to the east end of the Plaza to make room for them.
In the coming week:
In the coming week:
- The east wall will be waterproofed.
- The pavers will be mobilized and installed.
- The granite paver installation will continue.
- The south storefront will be installed.
- Handrail legs will be installed.
- Limestone installation will begin.
Wednesday, July 20, 2011
Weekly Construction Update: 7/20/2011
- The ceiling on the south end of Burrilll Hall (behind the cordoned off area) will be removed next week for electrical and plumbing work. Expect elevated noise levels.
- The sidewalk on Rush Street will be closed this Friday through Tuesday while it and the east wall are worked on.
- Concrete for the ramps will poured by early next week.
- The granite pavers will be delivered by the middle of next week.
- The dumpsters on Rush Street will be relocated to Huron Street to open up staging space for the pavers.
- The “Loading Zone” in front of the ramps on Huron Street will be converted into a “No Parking” zone.
- The installation of the granite pavers will begin late next week and continue for two weeks.
Wednesday, July 13, 2011
Weekly Construction Update: 7/13/2011
The following work is scheduled for the coming week:
- Pour concreate for the east upper stair ramp.
- Frame and pour east lower stairs.
- Strip forms and clean up of concrete.
Wednesday, July 6, 2011
Weekly Construction Update: 7/6/2011
In the coming week:
- The upper storefront steel installation will be completed.
- The framing of the west stairs will continue and the concrete will be poured.
- The east upper stairs and ramp will be framed and the concrete will be poured.
The following week:
- Strip forms and cleanup for the concrete will be done.
- Granite pavers will be delivered and installed.
Subscribe to:
Posts (Atom)