- The upper storefront steel installation will be completed.
- The framing of the west stairs will continue and the concrete will be poured.
- The east upper stairs and ramp will be framed and the concrete will be poured.
The following week:
- Strip forms and cleanup for the concrete will be done.
- Granite pavers will be delivered and installed.