Wednesday, December 14, 2011

Weekly Construction Update: 12/14/2011

This week the following work is expected:
  • Begin to set columns in lower level
  • Frame concrete walls on north plaza
  • Begin to pour walls on north plaza (weather permitting)
  • Install reinforcing steel/rebar
Next week the following work is expected:
  • Continue to set columns in the lower level
  • Excavate the underpinning of elevator three
  • Continued installation of waterproofing
  • Frame and install reinforcing steel for elevator three
  • Strip newly poured and set concrete walls on north plaza
  • Backfill new walls

Wednesday, December 7, 2011

Construction Progress In Pictures - Week of 12/5/2011

North wall waterproofing and framing for concrete


North storefront frame installed and ready for glass

New column footings in lower level


Weekly Construction Update: 12/7/2011

This week the following work is expected:
  • Installation of Lower level column footings. This will provide structural support to the builing.
  • Demolition of concrete beams in elevator shaft.
  • Removal of radiant pipes from the ceilings of vacant workspaces surrounding elevator shaft construction.
  • Continued waterproofing on lower level exterior.
Next week the following work is expected:
  • Continued installation of lower level column footings.
  • Continued concrete demolition in the elevator shaft.
  • Relocation of elevator shaft risers.
  • Continued removal of radiant pipes from the ceilings of the vacant workspaces around the elevator shaft.
  • Concrete footings on the north plaza will be back-filled and poured.