Wednesday, December 7, 2011

Weekly Construction Update: 12/7/2011

This week the following work is expected:
  • Installation of Lower level column footings. This will provide structural support to the builing.
  • Demolition of concrete beams in elevator shaft.
  • Removal of radiant pipes from the ceilings of vacant workspaces surrounding elevator shaft construction.
  • Continued waterproofing on lower level exterior.
Next week the following work is expected:
  • Continued installation of lower level column footings.
  • Continued concrete demolition in the elevator shaft.
  • Relocation of elevator shaft risers.
  • Continued removal of radiant pipes from the ceilings of the vacant workspaces around the elevator shaft.
  • Concrete footings on the north plaza will be back-filled and poured.

No comments:

Post a Comment