Weekly Construction Update: 1/4/2012

This week the following work is expected:
  • Installation of waterproofing in the shaft for the connector elevator
  • Pouring frames in the lower level
  • Ongoing excavation in the lower level
Next week the following work is expected:
  • Continued excavation in the lower level
  • Pouring frames in the lower level
  • Installation of shut-off valves for the existing radiant heat system

1 comment:

  1. the loan company that grants me loan of 5,000,000.00 USD When other loan investors has neglect my offer but mr benjamin lee granted me success loan.they are into directly in loan financing and project  in terms of investment. they provide financing solutions to companies and individuals seeking access to capital markets funds, they can helped you fund your project or expand your business.. Email Contact:::: Also  247officedept@gmail.com or Write on whatsapp Number  on    +1-(989-394-3740)