Thursday, June 14, 2012

Construction in Pictures: Week of 6/11/2012

Hole in office building roof for elevator room.

Concrete floor in link addition.

CMU walls on 5th floor.

Limestone walls on east side of plaza.

Weekly Construction Update: 6/14/2012

This week, the following work is expected:
  • Final connections in cooling tower, re-starting of chillers, and restoration of air conditioning
  • Pouring of concrete floor in Welcome Center
  • Removal of tree in plaza and excavation of sidewalk for tie-in of new water line to the City’s water main
  • Drywalling and taping of ceilings in lower level
  • Continued work on CMU walls on west side of office building
  • Beginning to install limestone on east side walls of plaza
  • Cut hole in roof of office building for elevator room
Next week, the following work is expected:

  • Complete installation of limestone walls on east side of plaza
  • Demo CMU walls in west offices around elevator shaft
  • Begin 1st coat of painting in lower level
  • Assemble and install pumps
  • Tile kitchen floor in lower level
  • Begin laying out walls in addition
  • Continue work on building over-hang ceilings

Friday, June 8, 2012

Construction In Pictures: Week of 6/4/2012

Duct in west offices

New panels in Great Hall (formerly Burill Hall) A/V room

Roof drain tie-in - in the link addition

Roof drain tie-in in addition

East wall limestone installation

Weekly Construction Update: 6/8/2012

This week the following work is expected:
·         Hanging drywall on the walls and ceilings in the lower level
·         Taping drywall seams in the lower level
·         Tying drains on link structure roof into drainage system
·         Ongoing installation of duct and pipe riser in the office tower
·         Installation of building overhang ceiling on the north plaza
·         Removal of tree on Rush Street to accommodate new water main tie-in
·         Installation of limestone on the east plaza wall (facing Rush Street)

Next week the following work is expected:
·         Continued taping of drywall seams in the lower level
·         Placement of a concrete slab in link/addition structure
·         Ongoing installation of duct and pipe riser in the office tower
·         Installation of building overhang ceiling on the north plaza
·         Tie-in of water main on Rush Street