This week, the following work is expected:
- Final connections in cooling tower, re-starting of chillers, and restoration of air conditioning
- Pouring of concrete floor in Welcome Center
- Removal of tree in plaza and excavation of sidewalk for tie-in of new water line to the City’s water main
- Drywalling and taping of ceilings in lower level
- Continued work on CMU walls on west side of office building
- Beginning to install limestone on east side walls of plaza
- Cut hole in roof of office building for elevator room
Next week, the following work is expected:
Complete installation of limestone walls on east side of plaza- Demo CMU walls in west offices around elevator shaft
- Begin 1st coat of painting in lower level
- Assemble and install pumps
- Tile kitchen floor in lower level
- Begin laying out walls in addition
- Continue work on building over-hang ceilings
No comments:
Post a Comment