Wednesday, June 8, 2011

Weekly Construction Update: 6/8/2011

Due to discovered existing conditions, the demolition of the east wall of the plaza has been halted.

In the coming week, Pepper Construction anticipates the following work:
·         Demo the existing waterproofing, weather permitting, Monday through Thursday
·         Install new storefront steel and new waterproofing Tuesday through Friday

If the demo of the existing waterproofing creates extreme noise conditions in the lobby, it will be closed during that work. The offices, however, will remain open. We will assess the noise level on Monday and notify the building if lobby closure will be necessary.

The following week, Pepper Construction plans to:
·         Begin framing for the concrete layout
·         Demo the south lobby plaster ceiling (behind the temporary partition wall)
·         Continue installation of upper storefront steel

Friday, June 3, 2011

Weekly Construction Update: 6/3/2011

The following work is scheduled for next week:

·         The entire east wall of the plaza will be demolished Monday through Wednesday.  The Rush Street sidewalk and the east side of the northeast plaza stairs will be closed during this work.
·         The south storefront will be demolished Wednesday through Friday.  Expect the work to be quite loud during that time.

During the following week, the existing waterproofing will be demolished and new waterproofing installed.