Wednesday, November 23, 2011

Construction Progress In Pictures - Week of 11/23/2011

South Plaza Ceiling 

North Plaza pavers arrive onsite


North wall waterproofing


North storefront framing

Weekly Construction Update: 11/23/2011

This week the following work is expected:
  • Concrete "cinder block" demolition on floors 2 - 4 and removal of concrete shaft
Next week the following work is expected:
  • Continuation of concrete block elevator shaft removal
  • Concrete "cinder block" demolition on floors 2 - 4 and removal of concrete shaft
  • Waterproofing on the north building wall (external lower level)
  • Excavation on the lower level
  • Column Footing framing & pouring on the lower level

Wednesday, November 16, 2011

Construction Progress In Pictures - Week of 11/14/2011

Vesting Sacristy

Vesting Sacristy area, post demo with waterproofing applied

Plaza ceiling

Plaza ceiling showing can lights and insullation

Plaza ceiling insullation and can lights, close-up

 
 North building wall - lower level, post excavation

 This area of the north wall is being prepared for waterproofing application


Weekly Construction Update: 11/16/2011

This week the following work is expected:
  • Excavation on the lower level
  • Installation of column footings on the lower level
  • Concrete "cinder block" demolition on floors 2 - 4 and removal of concrete shaft
  • Demolition of concrete elevator beams
  • Inspection of exterior building overhang ceiling
  • Insulation of building overhang ceiling and final preparation of ceiling before installation of soffit board (enclosure of ceiling)
  • Replacement of problem pavers on the south plaza

Next week the following work is expected:
  • Underpinning for west side plaza
  • Continuation of concrete beam demo
  • Continuation of concrete block elevator shaft removal
  • Installation of soffit board on exterior building overhang ceiling (pending inspection)
  • Pouring of concrete on the north building wall (external lower level)
  • Waterproofing on the north building wall (external lower level)

Thursday, November 10, 2011

Weekly Construction Update: 11/10/2011

This week the following work is taking place:
  • Demolition of lower level concrete
  • Construction of temporary partitions between staff work space and elevator construction zones on floors 2 - 4.
  • Demolition of wall panels surrounding concrete elevator shaft
  • Demolition of ceiling around existing elevator
  • Continued installation of framing and can lights for exterior building overhang ceiling

Next week the following work is expected:
  • Continued excavation around exterior north building wall (lower level)
  • Installation of footings for new columns (lower level)
  • Demolition and removal of concrete blocks surrounding existing elevator shaft
  • Continued demolition of ceiling surrounding existing elevator
  • Demolition of concrete beams related to existing elevator
  • Beginning to insulate and close exterior building overhang ceiling

Wednesday, November 2, 2011

Construction Progress Week of 10/31/2011

Vesting sacristy construction area
 Limestone wall in bottom of picture is to be demolished for link

 North plaza excavation
 Outdoor building overhang ceiling installation

Weekly Construction Update: 11/2/2011

This week the following work is expected to take place:
  • ongoing demolition of the roof of the vesting sacristy
  • demo of the limestone wall enclosing the vesting sacristy area
  • waterproofing around the vesting sacristy area
  • installation of storefront steel on north side of lobby
  • continued excavation of dirt and fill on north plaza with heavy equipment
  • clear north wall area of all dirt for waterproofing 
  • demolition on the lower level
  • construction zones staged on floors 2 - 5 in preparation for elevator shaft expansion work, beginning with floor 2 and ascending
  • continuing installation of outdoor building overhang ceiling.
Next week the following work is expected:
  • saw cutting a larger opening in the building on the lower level for the entrance of large equipment
  • demo and excavation of the new large entrance area
  • waterproofing east to west on the north building wall (external lower level)
  • continued installation of outdoor building overhang ceiling
  • underpinning of future link elevator
  • installation of beam footings
  • continued staging of construction zones on floors 2 - 5 in preparation for elevator work.