This week the following work is expected to take place:
- ongoing demolition of the roof of the vesting sacristy
- demo of the limestone wall enclosing the vesting sacristy area
- waterproofing around the vesting sacristy area
- installation of storefront steel on north side of lobby
- continued excavation of dirt and fill on north plaza with heavy equipment
- clear north wall area of all dirt for waterproofing
- demolition on the lower level
- construction zones staged on floors 2 - 5 in preparation for elevator shaft expansion work, beginning with floor 2 and ascending
- continuing installation of outdoor building overhang ceiling.
Next week the following work is expected:
- saw cutting a larger opening in the building on the lower level for the entrance of large equipment
- demo and excavation of the new large entrance area
- waterproofing east to west on the north building wall (external lower level)
- continued installation of outdoor building overhang ceiling
- underpinning of future link elevator
- installation of beam footings
- continued staging of construction zones on floors 2 - 5 in preparation for elevator work.