Thursday, February 23, 2012

Construction In Pictures: Week of 2/20/2012

Walls and ceiling in lower level

Office building elevator pit being framed for pouring concrete



A worker after demo complete on north section of cooling tower platform

Refuse of demo on north section of cooling tower platform

Progress on link elevator pit.


Abated sections (brown squares) of office building steel for tie into link

Weekly Construction Update: 2/23/2012

This week the following work has been completed or is expected:
  • Demo of concrete beams and limestone facade in dock/cooling tower area
  • Upwards extension (build up) of existing concrete block walls for connection with link
  • Preparation of 65 E Huron office building elevator pit for pouring concrete
  • Waterproofing, and backfilling link elevator pit
  • Coring in bathrooms located on the west side of restroom risers in 65 E Huron office building for new pipes.
  • HVAC, plumbing, and electrical work in the lower level (Burrill Hall) ceiling
  • Ongoing framing in the lower level
Next week the following work is expected:
  • Installation of steel supports in the dock/cooling tower area
  • Stripping, framing, and waterproofing walls of 65 E Huron office building elevator pit
  • Installation of piping in 65 E Huron office building bathrooms on west side of restroom risers
  • HVAC, electrical, plumbing, and framing ongoing in the lower level

Thursday, February 16, 2012

Construction Progress in Pictures - Week of 2/13/2012

Worker demoing wall in 65 E. Huron office tower restroom

Wall and fixtures removed from restroom

Wall construction on east side of lower level


Kitchen plumbing in place

65 E Huron building elevator pit excavation

Elevator pit excavation

Lower level laundry room plumbing

West end of 65 E Huron building being prepared to tie into link construction

Cooling tower platform demo

Cooling tower platform demo

Weekly Construction Update: 2/16/2012

This week the following work is expected:
  • Preparations for plumbing work, including laying floor protection on floors 2 - 4 of 65 E Huron office tower.
  • Removal of fixtures in selected 2nd, 3rd, and 4th floor restrooms
  • Open ceilings in selected 2nd, 3rd, and 4th floor restrooms
  • Open walls in selected restrooms and remove resulting debris
  • Demolition of concrete beams and walls in the dock/cooling tower area of the lower level
  • Continued work on pits of link and 65 E Huron building elevators
Next week the following work is expected:
  • Ongoing opening of walls in selected 2nd, 3rd, and 4th floor restrooms and removal of resulting debris
  • Begin reworking and installing new pipes in the selected restrooms
  • Any necessary abatement in selected restrooms
  • Demolition of old limestone in area where cooling tower stood
  • Continued work on pits of link and 65 E Huron building elevators

Thursday, February 2, 2012

Weekly Construction Update: 2/2/2012

This week the following work has been happening:
  • Continued work on 65 E Huron building elevator pit
  • Set-up scaffolding in the southwest corner of the lower level
  • Excavating, pouring concrete, and laying out walls in the lower level
  • Continued demo of the area where the cooling tower used to stand
  • Installation of underground plumbing under 65 E Huron
  • Installation of structural steel in the lower level
Next week the following work is expected:
  • Finish installing current section of underground plumbing
  • Pour more concrete and layout walls
  • Demo of concrete slab where the cooling tower was (southwest corner of lower level)
  • Other sawcutting and demo of concrete