This week the following work is expected:
- Preparations for plumbing work, including laying floor protection on floors 2 - 4 of 65 E Huron office tower.
- Removal of fixtures in selected 2nd, 3rd, and 4th floor restrooms
- Open ceilings in selected 2nd, 3rd, and 4th floor restrooms
- Open walls in selected restrooms and remove resulting debris
- Demolition of concrete beams and walls in the dock/cooling tower area of the lower level
- Continued work on pits of link and 65 E Huron building elevators
Next week the following work is expected:
- Ongoing opening of walls in selected 2nd, 3rd, and 4th floor restrooms and removal of resulting debris
- Begin reworking and installing new pipes in the selected restrooms
- Any necessary abatement in selected restrooms
- Demolition of old limestone in area where cooling tower stood
- Continued work on pits of link and 65 E Huron building elevators