Thursday, February 23, 2012

Weekly Construction Update: 2/23/2012

This week the following work has been completed or is expected:
  • Demo of concrete beams and limestone facade in dock/cooling tower area
  • Upwards extension (build up) of existing concrete block walls for connection with link
  • Preparation of 65 E Huron office building elevator pit for pouring concrete
  • Waterproofing, and backfilling link elevator pit
  • Coring in bathrooms located on the west side of restroom risers in 65 E Huron office building for new pipes.
  • HVAC, plumbing, and electrical work in the lower level (Burrill Hall) ceiling
  • Ongoing framing in the lower level
Next week the following work is expected:
  • Installation of steel supports in the dock/cooling tower area
  • Stripping, framing, and waterproofing walls of 65 E Huron office building elevator pit
  • Installation of piping in 65 E Huron office building bathrooms on west side of restroom risers
  • HVAC, electrical, plumbing, and framing ongoing in the lower level