This week the following work is expected to be completed:
· Install expansion joints (north plaza)
· Form permeable concrete area on the north plaza
· Receive delivery of granite pavers for north plaza
· Install pavers on the west side landing (north plaza)
· Review sample of permeable concrete on north plaza
· Continued mechanical, electrical, and plumbing work in the ceiling grid of the Great Hall (lower level)
· Filling/patching hole in north wall of the Lower Level
· Continue tiling lower level bathrooms
· Construct framing west of the lower level ramp
· Mechanical, electrical and plumbing work in the Welcome Center
· Installation of storefront window frames in the Welcome Center
· Install frame soffits in the Welcome Center
· Install door frames in the Welcome Center
Next week the following work is expected to be completed:
· Place permeable concrete area on the north plaza
· Install limestone on the west stairs of the north plaza
· Begin forming and placing the planters and curbs on the north plaza
· Continue mechanical, electrical, and plumbing work in the ceiling grid of the Great Hall (lower level)
· Continue tiling lower level restrooms
· Complete framing west of the lower level inside ramp
· Plumbing work in the lower level
· Plumbing inspection in one of the lower level restrooms
· Drywall and tape the framed section west of the ramp
· Continued mechanical, electrical, and plumbing work in the Welcome Center
· Begin installation of stairs from Welcome Center to Lower Level
· Install drop ceiling in the east section of the Great Hall