Last week the following work was completed:
·         Framing west of the lower level ramp
·         Plumbing work in a third lower level restroom
·         Installation of drop ceiling tile in the east half of the lower level
·         Continued mechanical, electrical, and plumbing installation in the Welcome Center
·         Framing of soffits in the Welcome Center
·         Installation of door frames in the Welcome Center
·         Placement of permeable concrete area on the North Plaza
·         Begin forming and placing curbs and planters on the North Plaza


This week the following work is expected:
·         Continued installation of the drop ceiling tiles in the east half of the lower level
·         Continued installation of fixtures in two lower level bathrooms
·         Inspection of plumbing work in the third lower level restroom currently under construction
·         Hanging drywall on framing west of ramp in lower level
·         Work on Welcome Center elevator
·         Installation of Welcome Center stairs
·         Inspection of Welcome Center walls
·         Hanging drywall in the Welcome Center
·         Begin framing for hard ceiling in Welcome Center
·         Continued forming and placement of curbs and planters on North Plaza, pouring concrete from east to west.
·         Begin installing stair treads on west stairs of North Plaza
·         Forming and placement of concrete slab on North Plaza

Next week the following work is expected:
·         Taping drywall seams west of ramp
·         Continued work on lower level ceiling grid on east side of lower level
·         Tiling and fixture installation in lower level restroom under construction
·         Continued work on Welcome Center elevator
·         Continued work on framing for hard ceiling in Welcome Center
·         Mechanical, electrical, and plumbing work in hard ceiling framing area
·         Continued installation of treads on west stairs of the North Plaza
·         Continued forming and placement of concrete slab on the North Plaza