This week the following work was expected:
· Placement of pavers on the street level of the north plaza
· Mechanical, electrical, and plumbing work in the Welcome Center ceiling
· Inspection of the Welcome Center ceiling
· Drywalling the Welcome Center ceiling
· Installation of fixtures in one of the lower level restrooms
Next week the following work is expected:
· Continued placement of pavers on the street level of the north plaza
· Continued drywalling of the Welcome Center ceiling
· Pour new cement floor in Welcome Center & Cathedral