This week the following work was expected:
· Tiling in Welcome Center restrooms
· Tape drywall seams on Welcome Center ceiling
· Continued tiling in lower level restrooms
· Continued installation of fixtures and accessories in lower level restrooms
· Mechanical, electrical, and plumbing work in the lower level ceiling grid
· Demolition of temporary wall, cabinets, and ceiling in Working Sacristy
· Open walls to install new power sources
· Place floor in Working Sacristy
· Build wall in Working Sacristy
· Install frame in Working Sacristy
· Begin roughing-in mechanical, electrical, and plumbing in Working Sacristy
· Ongoing installation of elevator in office tower building
· Build walls in west offices on second, third, and fourth floors of office tower
· Build soffits at ductwork in west offices
· Create soffits at windows in west offices
· Begin taping all floors in west offices of tower
Next week the following work is expected:
· Continued tiling in Welcome Center restrooms
· Application of the first coat of paint in the Welcome Center
· Continued work in the Welcome Center ceiling
· Continued installation of fixtures and accessories in lower level restrooms
· Installation of partitions in lower level restrooms
· Continued mechanical, electrical, and plumbing work in the Working Sacristy
· Taping drywall seams in the Working Sacristy
· Application of the first coat of paint in the Working Sacristy
· Installation of ceiling grid in Working Sacristy
· Continued work on the installation of the elevator in the office tower building
· Continued taping of floors in the west offices
· Begin work on the ceiling grid in the west offices
· Begin reworking lights in the west offices/around elevators
· Begin reworking HVAC in the west offices