This week the following work was expected:
· Continued tiling in Welcome Center restrooms
· Application of the first coat of paint in the Welcome Center
· Continued work in the Welcome Center ceiling
· Continued installation of fixtures and accessories in lower level restrooms
· Installation of partitions in lower level restrooms
· Continued mechanical, electrical, and plumbing work in the Working Sacristy
· Taping drywall seams in the Working Sacristy
· Application of the first coat of paint in the Working Sacristy
· Installation of ceiling grid in Working Sacristy
· Continued work on the installation of the elevator in the office tower building
· Continued taping of floors in the west offices
· Begin work on the ceiling grid in the west offices
· Begin reworking lights in the west offices/around elevators
· Fence set up to prepare for sidewalk replacement along Rush and Huron
Next week the following work is expected:
· Continued work on the Welcome Center ceiling
· Installation of Welcome Center restroom fixtures
· Mechanical, electrical and plumbing installation trim
· Begin installation of ceiling tiles in the Welcome Center
· Begin installation of floor tiles on the west side of the lower level
· Installation of lights in the Great Hall area (formerly Burrill Hall) of the lower level
· Installation of ceiling tiles in the lower level
· Installation of millwork in the Working Sacristy
· Begin installation of ceiling tiles in the Working Sacristy
· Continued work on the installation of the elevator in the office tower building
· Continued work on the ceiling grid in the west offices
· Continued work on the lights in the west offices
· Continued work on the HVAC in the west offices
· Begin installation of ceiling tiles in the west offices
· Continued sidewalk replacement along Rush and Huron