Weekly Construction Update: 9/28/2012

This week the following work was expected:
·         Continued tiling in Welcome Center restrooms
·         Application of the first coat of paint in the Welcome Center
·         Continued work in the Welcome Center ceiling
·         Continued installation of fixtures and accessories in lower level restrooms
·         Installation of partitions in lower level restrooms
·         Continued mechanical, electrical, and plumbing work in the Working Sacristy
·         Taping drywall seams in the Working Sacristy
·         Application of the first coat of paint in the Working Sacristy
·         Installation of ceiling grid in Working Sacristy
·         Continued work on the installation of the elevator in the office tower building
·         Continued taping of floors in the west offices
·         Begin work on the ceiling grid in the west offices
·         Begin reworking lights in the west offices/around elevators
·         Fence set up to prepare for sidewalk replacement along Rush and Huron


Next week the following work is expected:
·         Continued work on the Welcome Center ceiling
·         Installation of Welcome Center restroom fixtures
·         Mechanical, electrical and plumbing installation trim
·         Begin installation of ceiling tiles in the Welcome Center
·         Begin installation of floor tiles on the west side of the lower level
·         Installation of lights in the Great Hall area (formerly Burrill Hall) of the lower level
·         Installation of ceiling tiles in the lower level
·         Installation of millwork in the Working Sacristy
·         Begin installation of ceiling tiles in the Working Sacristy
·         Continued work on the installation of the elevator in the office tower building
·         Continued work on the ceiling grid in the west offices
·         Continued work on the lights in the west offices
·         Continued work on the HVAC in the west offices
·         Begin installation of ceiling tiles in the west offices
·         Continued sidewalk replacement along Rush and Huron