Last week the following work was expected to be completed:
· Demolition of concrete in the dock area ally
· Chipping top south foundation wall at the loading dock
· Digging for grade beams for dock structure
· Framing and placement of grade beams and stone in the loading dock area
· Hanging drywall on the west side of the lower level
· Taping drywall seams on the west side of the lower level
· Continued tiling work in lower level restrooms
· Work in the pump room
· Hanging drywall in the Welcome Center addition
· Continued framing of the hard ceiling in the Welcome Center
· Taping drywall seams in the Welcome Center
· Reworking of power to the elevator shaft in the office tower
· Patching of CMU/cinder block walls
· Installation of safety rail around elevator work area in the office tower
This week the following work is expected:
· Continued framing and placement of grade beam and stone in the loading dock area
· Placement of concrete slab in the loading dock ally
· Framing for stairs and landing at the loading dock
· Installation of rebar in the dock area
· Continued tiling work in lower level restrooms
· Installation of ceiling grid on the west side of the lower level
· Installation of fixtures and accessories in lower level restrooms
· Mechanical, electrical, and plumbing work in the ceiling grid, west side of lower level
· Continued framing of the hard ceiling in the Welcome Center addition
· Rough-in mechanical, electrical and plumbing in the Welcome Center ceiling
· Continued taping of drywall seams in the Welcome Center
· Inspection of Welcome Center ceiling
· Tiling in Welcome Center restrooms
· Drywalling Welcome Center ceilings
· Continued patching of CMU walls around the office tower elevator shaft
· Installation of ductwork in the west office tower rooms
· Demolition of walls in the area of the elevator on the second floor
· Removal of some carpet in west offices