Tuesday, September 4, 2012

Construction Update: 9/4/2012


Last week the following work was expected to be completed:
·         Demolition of concrete in the dock area ally
·         Chipping top south foundation wall at the loading dock
·         Digging for grade beams for dock structure
·         Framing and placement of grade beams and stone in the loading dock area
·         Hanging drywall on the west side of the lower level
·         Taping drywall seams on the west side of the lower level
·         Continued tiling work in lower level restrooms
·         Work in the pump room
·         Hanging drywall in the Welcome Center addition
·         Continued framing of the hard ceiling in the Welcome Center
·         Taping drywall seams in the Welcome Center
·         Reworking of power to the elevator shaft in the office tower
·         Patching of CMU/cinder block walls
·         Installation of safety rail around elevator work area in the office tower


This week the following work is expected:
·         Continued framing and placement of grade beam and stone in the loading dock area
·         Placement of concrete slab in the loading dock ally
·         Framing for stairs and landing at the loading dock
·         Installation of rebar in the dock area
·         Continued tiling work in lower level restrooms
·         Installation of ceiling grid on the west side of the lower level
·         Installation of fixtures and accessories in lower level restrooms
·         Mechanical, electrical, and plumbing work in the ceiling grid, west side of lower level
·         Continued framing of the hard ceiling in the Welcome Center addition
·         Rough-in mechanical, electrical and plumbing in the Welcome Center ceiling
·         Continued taping of drywall seams in the Welcome Center
·         Inspection of Welcome Center ceiling
·         Tiling in Welcome Center restrooms
·         Drywalling Welcome Center ceilings
·         Continued patching of CMU walls around the office tower elevator shaft
·         Installation of ductwork in the west office tower rooms
·         Demolition of walls in the area of the elevator on the second floor
·         Removal of some carpet in west offices

No comments:

Post a Comment