Wednesday, December 14, 2011

Weekly Construction Update: 12/14/2011

This week the following work is expected:
  • Begin to set columns in lower level
  • Frame concrete walls on north plaza
  • Begin to pour walls on north plaza (weather permitting)
  • Install reinforcing steel/rebar
Next week the following work is expected:
  • Continue to set columns in the lower level
  • Excavate the underpinning of elevator three
  • Continued installation of waterproofing
  • Frame and install reinforcing steel for elevator three
  • Strip newly poured and set concrete walls on north plaza
  • Backfill new walls

Wednesday, December 7, 2011

Construction Progress In Pictures - Week of 12/5/2011

North wall waterproofing and framing for concrete


North storefront frame installed and ready for glass

New column footings in lower level


Weekly Construction Update: 12/7/2011

This week the following work is expected:
  • Installation of Lower level column footings. This will provide structural support to the builing.
  • Demolition of concrete beams in elevator shaft.
  • Removal of radiant pipes from the ceilings of vacant workspaces surrounding elevator shaft construction.
  • Continued waterproofing on lower level exterior.
Next week the following work is expected:
  • Continued installation of lower level column footings.
  • Continued concrete demolition in the elevator shaft.
  • Relocation of elevator shaft risers.
  • Continued removal of radiant pipes from the ceilings of the vacant workspaces around the elevator shaft.
  • Concrete footings on the north plaza will be back-filled and poured.

Wednesday, November 23, 2011

Construction Progress In Pictures - Week of 11/23/2011

South Plaza Ceiling 

North Plaza pavers arrive onsite


North wall waterproofing


North storefront framing

Weekly Construction Update: 11/23/2011

This week the following work is expected:
  • Concrete "cinder block" demolition on floors 2 - 4 and removal of concrete shaft
Next week the following work is expected:
  • Continuation of concrete block elevator shaft removal
  • Concrete "cinder block" demolition on floors 2 - 4 and removal of concrete shaft
  • Waterproofing on the north building wall (external lower level)
  • Excavation on the lower level
  • Column Footing framing & pouring on the lower level

Wednesday, November 16, 2011

Construction Progress In Pictures - Week of 11/14/2011

Vesting Sacristy

Vesting Sacristy area, post demo with waterproofing applied

Plaza ceiling

Plaza ceiling showing can lights and insullation

Plaza ceiling insullation and can lights, close-up

 
 North building wall - lower level, post excavation

 This area of the north wall is being prepared for waterproofing application


Weekly Construction Update: 11/16/2011

This week the following work is expected:
  • Excavation on the lower level
  • Installation of column footings on the lower level
  • Concrete "cinder block" demolition on floors 2 - 4 and removal of concrete shaft
  • Demolition of concrete elevator beams
  • Inspection of exterior building overhang ceiling
  • Insulation of building overhang ceiling and final preparation of ceiling before installation of soffit board (enclosure of ceiling)
  • Replacement of problem pavers on the south plaza

Next week the following work is expected:
  • Underpinning for west side plaza
  • Continuation of concrete beam demo
  • Continuation of concrete block elevator shaft removal
  • Installation of soffit board on exterior building overhang ceiling (pending inspection)
  • Pouring of concrete on the north building wall (external lower level)
  • Waterproofing on the north building wall (external lower level)

Thursday, November 10, 2011

Weekly Construction Update: 11/10/2011

This week the following work is taking place:
  • Demolition of lower level concrete
  • Construction of temporary partitions between staff work space and elevator construction zones on floors 2 - 4.
  • Demolition of wall panels surrounding concrete elevator shaft
  • Demolition of ceiling around existing elevator
  • Continued installation of framing and can lights for exterior building overhang ceiling

Next week the following work is expected:
  • Continued excavation around exterior north building wall (lower level)
  • Installation of footings for new columns (lower level)
  • Demolition and removal of concrete blocks surrounding existing elevator shaft
  • Continued demolition of ceiling surrounding existing elevator
  • Demolition of concrete beams related to existing elevator
  • Beginning to insulate and close exterior building overhang ceiling

Wednesday, November 2, 2011

Construction Progress Week of 10/31/2011

Vesting sacristy construction area
 Limestone wall in bottom of picture is to be demolished for link

 North plaza excavation
 Outdoor building overhang ceiling installation

Weekly Construction Update: 11/2/2011

This week the following work is expected to take place:
  • ongoing demolition of the roof of the vesting sacristy
  • demo of the limestone wall enclosing the vesting sacristy area
  • waterproofing around the vesting sacristy area
  • installation of storefront steel on north side of lobby
  • continued excavation of dirt and fill on north plaza with heavy equipment
  • clear north wall area of all dirt for waterproofing 
  • demolition on the lower level
  • construction zones staged on floors 2 - 5 in preparation for elevator shaft expansion work, beginning with floor 2 and ascending
  • continuing installation of outdoor building overhang ceiling.
Next week the following work is expected:
  • saw cutting a larger opening in the building on the lower level for the entrance of large equipment
  • demo and excavation of the new large entrance area
  • waterproofing east to west on the north building wall (external lower level)
  • continued installation of outdoor building overhang ceiling
  • underpinning of future link elevator
  • installation of beam footings
  • continued staging of construction zones on floors 2 - 5 in preparation for elevator work.

Wednesday, October 26, 2011

Construction Progress Week of 10/24/2011

demolition of roof over vesting sacristy

 North plaza demo and excavation

 More vesting sacristy room demo

Weekly Construction Update: 10/26/2011

This week the following work is expected to take place:
  • demolition of the roof of the vesting sacristy
  • demo and excavation of the North plaza
  • cutting walls on the lower level
  • competion of asbestos removal on the lower level
  • installation of ceiling on external building overhang.
Next week the following work is expected:
  • demolition of concrete on the lower level
  • work on the underpining for the new elevator
  • installation of storefront steel on the north plaza
  • installation of storefront glass on the north plaza

Wednesday, October 19, 2011

Weekly Construction Update: 10/19/2011

This week the following work is expected to take place:
  • Removal of asbestos from the lower level
  • Demo and excavation at and up to the north wall of the building
  • External demolition at the location of the vesting sacristy
All of these projects will continue into the following week (10/24 - 10/28)

Wednesday, October 5, 2011

Construction Progress Week of 10/3/2011

Demolition of the north plaza


Weekly Construction Update: 10/5/2011

This week, the following work has or is expected to take place:
  • continuing plaza demo
  • soft (minimal vibrations) interior demolition of the vesting sacristy, including mechanical, electrical, and plumbing
  • removal of waterproofing on the north plaza/lower level of building
  • concrete framing on the north plaza
Next week, the following work is expected:
  • continuation of vesting sacristy demo
  • continuation of concrete framing
  • storefront steel work on north plaza lower level
  • asbestos abatement of some pipes

Wednesday, September 28, 2011

Construction Progress Week Of 9/26/2011

Views of recent demo and construction on the north plaza at 65 E Huron Street





Weekly Construction Update: 9/28/2011

This week demolition of north plaza is ongoing.

Next week, the following work is expected:
  • Continuation of north plaza demo
  • Demolition of portions of the vesting sacristy
  • Removal of waterproofing along the north side
  • Concrete work

Wednesday, September 21, 2011

Construction Progress Week of 9/19/2011


Views of the south plaza.





Views of the north plaza






Weekly Construction Update: 9/21/2011

This week the following work is expected or has already taken place:
  • Orient lobby for primary entrance via the south plaza
  • Install temporary fencing around north plaza to establish construction zone
  • Demolish the north side store front including overhang
  • Removal of trees in north plaza garden
Next week the following is expected to take place:
  • Complete storefront demo
  • Begin demolition of north plaza, including break-up and removal of concrete.

Thursday, September 15, 2011

Construction Progress Week Of 9/12/2011

When entering via the south plaza, expect to see this open cavity in the overhang. It will be closed later in construction. It is secure for walking under.

Completed ramp. Railings to be installed.

Arial view of south plaza.

 The sunken rectangular cavity in the wall will be a planter.

Limestone wall and granite cap installed at south plaza Rush Street entrance.

Installing granite caps on Rush Street wall.

Rush Street property wall.