Thursday, August 18, 2011

Weekly Construction Update: 8/18/2011

This coming week, the following work is expected:
  • Construction zone moves to lower level of Diocesan Center - construction access only
  • Final installation of the pavers
  • Install the storefront- glass & temporary South E/W doors
  • Continue installing the overhang lighting
  • Continue grouting the pavers
  • Begin laminating the overhang 
  • Begin installing limestone
  • Install handrail brackets and handrails
The following week, contractors will:
  • Continue installing overhang lighting
  • Continue installing limestone
  • Continue handrail brackets and handrails
  • Begin installing stairs