- Finish ADA ramp into the Cathedral
- Finish building interior partitions on lower level
- Finish installing granite pavers
- Finish installing limestone clips
- Re-waterproof where the limestone clips were installed
- Install the storefront glass and temporary doors on the southeast and southwest entrances
- Continue exploratory work on lower level
- Begin installing limestone
The following week, contractors will:
- Continue installing limestone
- Begin grouting the pavers