Friday, March 16, 2012

Weekly Construction Update: 3/16/2012

This week the following work is expected:
  • Waterproofing along east plaza/Rush Street sidewalk walk
  • Complete pipe work in 2nd – 4th floor bathrooms
  • Begin to frame for drywall patching in 2nd – 4th floor bathrooms
  • Erect steel and install decking in link structure
  • Finish removing ramp from the lower level
  • Continue framing and ceiling installation in the lower level
  • Build concrete block walls around office building elevator shaft in the lower level
  • Build concrete block walls around pump room in the lower level

Next week the following work is expected:
  • Position pavers and set-up for paver installation on upper level of north plaza
  • Finish patching walls in office building bathrooms.
  • Tile 2nd – 4th floor bathroom walls where tile had to be removed for riser work
  • Continue to erect steel and install decking in link structure
  • Drain work in the lower level
  • Excavate lower level stairwell footings and place new ones
  • Build stair walls
  • Continue framing and ceiling installation in the lower level
  • Build concrete block walls around link elevator shaft in the lower level
  • Continued work on ramp in the lower level
  • Plumbing work in lower level pump room

No comments:

Post a Comment