This week the following work is expected:
- Waterproofing along east plaza/Rush Street sidewalk walk
- Complete pipe work in 2nd – 4th floor bathrooms
- Begin to frame for drywall patching in 2nd – 4th floor bathrooms
- Erect steel and install decking in link structure
- Finish removing ramp from the lower level
- Continue framing and ceiling installation in the lower level
- Build concrete block walls around office building elevator shaft in the lower level
- Build concrete block walls around pump room in the lower level
Next week the following work is expected:
- Position pavers and set-up for paver installation on upper level of north plaza
- Finish patching walls in office building bathrooms.
- Tile 2nd – 4th floor bathroom walls where tile had to be removed for riser work
- Continue to erect steel and install decking in link structure
- Drain work in the lower level
- Excavate lower level stairwell footings and place new ones
- Build stair walls
- Continue framing and ceiling installation in the lower level
- Build concrete block walls around link elevator shaft in the lower level
- Continued work on ramp in the lower level
- Plumbing work in lower level pump room