This week the following work is expected:
- Continuing to erect steel and decking for the link structure
- Building concrete block wall
- Roughing in of the drain on the roof
- Building walls around the stairs in the former lower level ramp area
- Prepping and pour stairs in the former lower level ramp area
- Laying out and beginning to set pavers on the upper tier of the north plaza
- Continued work on the water feature (ground level of the north plaza) including forming the structure and roughing in the electricity
Next week the following work is expected:
- Finishing roughing in the drain on the roof of the link structure
- Roof and skylight blocking
- Framing in the link structure
- Finishing upper stairs in the former lower level ramp area
- Beginning to prep lower stairs in the former lower level ramp area
- Setting pavers on the upper tier of the north plaza
- Electric work on the upper tier of the north plaza
- Installing rebar, embeds, and placing water feature on the ground level of the north plaza
- Demoing slab concrete to the end of the wall on the ground level of the lower plaza