This week the following work was scheduled to be completed:
- Frame walls in the lower level
- Electrical and plumbing work in the ceiling of the lower level
- Patching CMU (cinder block) walls
- Setting pavers on the upper tier of the north plaza
- Demoing and prepping the concrete slab that was the old north plaza (main plaza level)
- Placing new concrete on the main plaza level
- Detail framing in the link structure
Next week the following work is expected to take place:
- Continued framing in the lower level of the 65 E Huron office building
- Installing door frames in the lower level
- Inspection of wall construction in the lower level
- Continuing to set pavers on the upper tier of the north plaza
- Install fire department piping on the upper tier of the north plaza
- Set limestone on the upper tier of the north plaza
- Install part of building overhand ceiling