This week the following work was expected:
· CMU/cinder block wall patching around elevator doors
· Reworking lights in and around west offices
· Tile installation in the laundry room (lower level)
· Installation of millwork (cabinetry, etc) in the laundry room (lower level)
· Continued installation of ceiling tiles in the lower level
· Continued clearing out Great Hall area to prepare for finishing
· Installation of ceiling tiles in the Welcome Center
· Construction of a temporary wall in the Welcome Center to separate construction site from Cathedral
· Continued sidewalk replacement along Rush and Huron including replacement of curbs, adjustment of utility covers, and begin pouring concrete slabs.
Next week the following work is expected:
· Installation of elevator doors
· Continued tiling in the laundry room (lower level)
· Continued Installation of millwork in the laundry room
· Final painting of doors and frames in the lower level
· Installation of miscellaneous hardware in the lower level
· Installation of a handrail on lower level stairs
· Continued installation of Welcome Center ceiling
· Installation of sprinkler system and lights in the Welcome Center
· Continued construction of the temporary wall between the construction area and Cathedral
· Continued sidewalk replacement along Rush and Huron