Sunday, October 14, 2012

Weekly Construction Update: 10/14/2012

This week the following work was expected:
·         CMU/cinder block wall patching around elevator doors
·         Reworking lights in and around west offices
·         Tile installation in the laundry room (lower level)
·         Installation of millwork (cabinetry, etc) in the laundry room (lower level)
·         Continued installation of ceiling tiles in the lower level
·          Continued clearing out Great Hall area to prepare for finishing
·         Installation of ceiling tiles in the Welcome Center
·         Construction of a temporary wall in the Welcome Center to separate construction site from Cathedral
·         Continued sidewalk replacement along Rush and Huron including replacement of curbs, adjustment of utility covers, and begin pouring concrete slabs.

Next week the following work is expected:
·         Installation of elevator doors
·         Continued tiling in the laundry room (lower level)
·         Continued Installation of millwork in the laundry room
·         Final painting of doors and frames in the lower level
·         Installation of miscellaneous hardware in the lower level
·         Installation of a handrail on lower level stairs
·         Continued installation of Welcome Center ceiling
·         Installation of sprinkler system and lights in the Welcome Center
·         Continued construction of the temporary wall between the construction area and Cathedral
·         Continued sidewalk replacement along Rush and Huron

Note: see map indicating modified building access to begin Mon. 10/22.

No comments:

Post a Comment