This week the following work was expected:
· Ongoing preparation of floors for tiling in the Welcome Center
· Begin tiling Welcome Center floor
· Installation of southeast window in the Welcome Center
· Ongoing mechanical, electrical, and plumbing work in the Welcome Center ceiling
· Installation of tile in the Working Sacristy
· Installation of ceiling tiles in the Welcome Center
· Installation of Welcome Center storefront
· Finishing-up drywall installation in the Lower Level
· Installation of millwork in the Lower Level Laundry Room
· Plumbing work in the Lower Level Laundry Room
· Continued drywalling and painting in the Office Tower around the elevator construction area
· Installation of doors and hardware in the west Office Tower hallways
· Frame and pour the east ramp retaining wall (north plaza)
· Backfill with gravel around east ramp retaining wall
Next week the following work is expected:
· Painting in the Office Tower west offices
· Carpet installation in the west offices
· Ongoing installation of the Office Tower elevator
· Continued framing and hanging drywall in the elevator lobbies on each floor
· Work on the ceiling around the elevators
· Ongoing preparation of floors for tiling in the Welcome Center
· Ongoing tiling of the Welcome Center floor
· Installation and wiring of loading dock gates
· Installation of wall covering in the Welcome Center
· Installation of millwork in the acolyte room
· Final floor tiling in the lower level
· Installation of door frame in the lower level
· Painting the stairwell leading from the lower level/Great Hall to the current lobby
· Clear equipment etc. from Burrill Hall to allow floor to be prepped for carpeting
· Continued backfilling in east ramp
· Shotcrete and waterproofing of the Cathedral foundation wall (East wall along North plaza)
· Exterior cleaning of Office Tower
*The sidewalk on Huron will be closed through 11/9/2012. Be prepared to seek alternate routes to enter the office building*