This week the following work was expected:
· Continued work on the Welcome Center ceiling
· Installation of Welcome Center restroom fixtures
· Mechanical, electrical and plumbing installation trim
· Begin installation of ceiling tiles in the Welcome Center
· Begin installation of floor tiles on the west side of the lower level
· Installation of lights in the Great Hall area (formerly Burrill Hall) of the lower level
· Installation of ceiling tiles in the lower level
· Installation of millwork in the Working Sacristy
· Begin installation of ceiling tiles in the Working Sacristy
· Continued work on the installation of the elevator in the office tower building
· Continued work on the ceiling grid in the west offices
· Continued work on the lights in the west offices
· Continued work on the HVAC in the west offices
· Begin installation of ceiling tiles in the west offices
· Continued sidewalk replacement along Rush and Huron
Next week the following work is expected:
· CMU/cinder block wall patching around elevator doors
· Installation of ceiling tiles in the west offices
· Framing and hanging drywall in the hallways near the elevator and west offices
· Tile installation in the laundry room (lower level)
· Installation of millwork (cabinetry, etc) in the laundry room (lower level)
· Continued installation of ceiling tiles in the lower level
· Begin clearing out Great Hall area to prepare for finishing
· Installation of ceiling tiles in the Welcome Center
· Continued sidewalk replacement along Rush and Huron