This week the following work was expected:
· Ongoing millwork installation in the Welcome Center
· Painting in the Welcome Center and Great Hall
· Carpeting in the Welcome Center and Great Hall
· Ongoing floor tile in the Welcome Center
· Ongoing installation of doors and hardware in the Welcome Center
· Ongoing paver installation on N. Plaza
· Placing soil and trees around the labyrinth area
· Ongoing elevator work in office tower
· Installation of carpet tiles in the office tower, floors 2 – 4
· Ongoing exterior cleaning of Office Tower
·
Next week the following work is expected:
· Painting in the Welcome Center
· Ongoing paver installation on N. Plaza
· Ongoing installation of carpet tiles in the office tower, floors 3 – 4
· Ongoing elevator work in office tower
· Cleaning and inspections of the Welcome Center and Great Hall
· Ongoing exterior cleaning of Office Tower