This week the following work was expected:
· Painting in the Office Tower west offices
· Carpet installation in the west offices
· Ongoing installation of the Office Tower elevator
· Continued framing and hanging drywall in the elevator lobbies on each floor
· Work on the ceiling around the elevators
· Ongoing preparation of floors for tiling in the Welcome Center
· Ongoing tiling of the Welcome Center floor
· Installation and wiring of loading dock gates
· Installation of wall covering in the Welcome Center
· Installation of millwork in the acolyte room
· Final floor tiling in the lower level
· Installation of door frame in the lower level
· Painting the stairwell leading from the lower level/Great Hall to the current lobby
· Clear equipment etc. from Great Hall (Burrill Hall) to allow floor to be prepped for carpeting
· Continued backfilling in east ramp
· Shotcrete and waterproofing of the Cathedral foundation wall (East wall along North plaza)
· Concrete pouring north plaza ramp
· Preparation for exterior cleaning of Office Tower
Next week the following work is expected:
· Exterior cleaning of Office Tower
· Ongoing work on the ceiling grid in the Office Tower west offices and elevator lobbies, floor 2 -4
· Reworking of mechanical, electrical, and plumbing in the Office Tower west offices
· Finish installing drop ceiling tiles in west offices
· Painting in west offices
· Begin carpeting in west offices
· Concrete pouring of the following plaza components/areas: stairs to the lower level, west sidewalk, north plaza ramp, bench piers, sign foundations
· Ongoing installation of floor tile in Welcome Center
· Painting in the Welcome Center (into Saturday)
· Installation of vinyl composition tile in slop sink/dock area
· Installation of stair 3 handrails
· Installation of doors and hardware in the Addition
· Installation of storefront doors in Welcome Center
· Final painting in Lower Level and Great Hall area
· Prep of Great Hall floor for carpeting
· Begin carpeting of the Great Hall floor
· Installation of Lower Level stair handrails
· Installation of doors and hardware in the lower level
*The sidewalk on Huron will be closed through the end of next week (11/9/2012). Be prepared to seek alternate routes to enter the office building*
No comments:
Post a Comment