This week the following work is expected:
· Roofing on the link structure
· Installation of concrete wall in the offices in the west end of the office building
· Installation of duct and pipe riser in the area of the west offices
· Work on lower level ceiling, including roughing in can lights and final framing work
Next week the following work is expected:
· Finishing roofing on the link structure
· Installation of skylight in the link structure ceiling/roof
· Placement of a concrete slab associated with the link structure
· Delivery of new cooling tower
· Continued installation of duct and pipe riser in the area of the west offices
· Framing in riser in the area of the west offices
· Continued work on the lower level ceiling, including roughing in can lights, final framing work, and roughing in A/V components
· Delivery of limestone for walls abutting the sidewalk on Rush Street. Installation of limestone on walls will commence after delivery.