Wednesday, May 9, 2012

Weekly Construction Update: 5/9/2012

This week the following work is expected:
  • Installation of rebar and concrete block wall in the west offices, floors 2 - 5 of the office tower
  • Installation work for ceiling lights in the lower level
  • Installation of more steel in the SW section link area
  • Setting limestone - north plaza
Next week the following work is expected:
  • Continued work on installing concrete block walls in the west offices, floors 2 - 5 of the office tower
  • Begin to drywall ceilings in the lower level
  • Begin roofing the link structure
  • Placing limestone end caps on the north plaza walls
  • Preparing surface for new concrete slabs to be poured on the lower level of the north plaza