This week the following work is expected:
· Finishing roofing on the link structure
· Tie in roof drains
· Installation of skylight in the link structure ceiling/roof
· Installation of steel cooling tower enclosure
· Continued installation of duct and pipe riser in the area of the west offices
· Installation of duct and pipe riser in the area of the west offices
· Installation of duct work for air handlers in office building
· Continued work on the lower level ceiling, including roughing in can lights, final framing work, and roughing in A/V components
· Installation of limestone on East Plaza wall
Next week the following work is expected:
· Continued installation of limestone on East Plaza wall
· Framing in riser in the area of the west offices
· Installation of drywall in lower level ceilings