Thursday, May 31, 2012

Weekly Construction Update: 5/31/2012

This week the following work is expected:
·         Finishing roofing on the link structure & cooling tower pad
·         Continued installation of duct and pipe riser in the area of the west offices
·         Installation of cooling tower
·         Installation of duct work for air handlers in office building
·         Continued work on the lower level ceiling, including roughing in can lights, final framing work, and roughing in A/V components
·         Installation of limestone on East Plaza wall

Next week the following work is expected:
·         Continued installation of limestone on East Plaza wall
·         Framing in riser in the area of the west offices
·         One tree removed on rush for new water main connection
·         Installation of sliding glass door in lobby