Wednesday, July 27, 2011

Weekly Construction Update: 7/27/2011

The pavers have been delivered!  The dumpster on Rush Street has been relocated to the east end of the Plaza to make room for them.

In the coming week:
  • The east wall will be waterproofed.
  • The pavers will be mobilized and installed.
During the following week:
  • The granite paver installation will continue.
  • The south storefront will be installed.
  • Handrail legs will be installed.
  • Limestone installation will begin.
Note that the "Loading Zone" on Huron Street will soon become a "No Parking" zone.