Wednesday, October 26, 2011

Weekly Construction Update: 10/26/2011

This week the following work is expected to take place:
  • demolition of the roof of the vesting sacristy
  • demo and excavation of the North plaza
  • cutting walls on the lower level
  • competion of asbestos removal on the lower level
  • installation of ceiling on external building overhang.
Next week the following work is expected:
  • demolition of concrete on the lower level
  • work on the underpining for the new elevator
  • installation of storefront steel on the north plaza
  • installation of storefront glass on the north plaza