Weekly Construction Update: 9/14/2012

This week the following work was expected:
·         Frame stair riser in the loading dock area
·         Place landing and stairs in the loading dock area
·         Continued tiling, installation of fixtures and accessories in lower level restrooms
·         Mechanical, electrical, and plumbing work in the ceiling, west end of lower level
·         Mechanical, electrical, and plumbing work in the ceiling of the Welcome Center
·         Taping drywall seams on the walls and ceiling in the Welcome Center
·         Tiling in Welcome Center restrooms.
·         Begin installation of new office building elevator
·         Demolition/removal of carpet in west offices
·         Construction of concrete block walls in west offices (surrounding new elevator) on the third and fourth floors.

Next week the following work is expected:
·         Strip bottom forms from previous concrete work in the loading dock area after one week drying time.
·         Build walls in the dock area
·         Installation of steel on the south wall of the loading dock alley area
·         Continued installation of fixtures and accessories in lower level restrooms
·         Installation of stall partitions in lower level restrooms
·         Installation of ceiling tiles in the lower level
·         Continued tiling in Welcome Center restrooms
·         Continued taping of drywall seams on Welcome Center ceiling
·         Work on Welcome Center stairs
·         Application of first coat of paint in the Welcome Center
·         Mechanical, electrical, and plumbing work in Welcome Center
·         Begin installation of fixtures in the Welcome Center restrooms