Friday, October 26, 2012

Weekly Construction Update: 10/26/2012

This week the following work was expected:

·         Ongoing preparation of floors for tiling in the Welcome Center
·         Begin tiling Welcome Center floor
·         Installation of southeast window in the Welcome Center
·         Ongoing mechanical, electrical, and plumbing work in the Welcome Center ceiling
·         Installation of tile in the Working Sacristy
·         Installation of ceiling tiles in the Welcome Center
·         Installation of Welcome Center storefront
·         Finishing-up drywall installation in the Lower Level
·         Installation of millwork in the Lower Level Laundry Room
·         Plumbing work in the Lower Level Laundry Room
·         Continued drywalling and painting in the Office Tower around the elevator construction area
·         Installation of doors and hardware in the west Office Tower hallways
·         Frame and pour the east ramp retaining wall (north plaza)
·         Backfill with gravel around east ramp retaining wall

Next week the following work is expected:
·         Painting in the Office Tower west offices
·         Carpet installation in the west offices
·         Ongoing  installation of the Office Tower elevator
·         Continued framing and hanging drywall in the elevator lobbies on each floor
·         Work on the ceiling around the elevators
·         Ongoing preparation of floors for tiling in the Welcome Center
·         Ongoing tiling of the Welcome Center floor
·         Installation and wiring of loading dock gates
·         Installation of wall covering in the Welcome Center
·         Installation of millwork in the acolyte room
·         Final floor tiling in the lower level
·         Installation of door frame in the lower level
·         Painting the stairwell leading from the lower level/Great Hall to the current lobby
·         Clear equipment etc. from Burrill Hall to allow floor to be prepped for carpeting
·         Continued backfilling in east ramp
·         Shotcrete and waterproofing of the Cathedral foundation wall (East wall along North plaza)
·       Exterior cleaning of Office Tower

*The sidewalk on Huron will be closed through 11/9/2012. Be prepared to seek alternate routes to enter the office building* 