Wednesday, August 24, 2011

Weekly Construction Update: 8/24/2011

This week, the following work is expected:
  • Finish ADA ramp into the Cathedral
  • Finish building interior partitions on lower level
  • Finish installing granite pavers
  • Finish installing limestone clips
  • Re-waterproof where the limestone clips were installed
  • Install the storefront glass and temporary doors on the southeast and southwest entrances
  • Continue exploratory work on lower level
  • Begin installing limestone
The following week, contractors will:
  • Continue installing limestone
  • Begin grouting the pavers

No comments:

Post a Comment