Wednesday, August 31, 2011

Weekly Construction Update: 8/31/2011

This week, the following work is expected:
  • Complete the south storefront glass installation.
  • Install granite caps on the wall that runs east/west.
  • Install limestone on the wall that runs north/south.
  • Install east stairs.
  • Install hand rails.
Next week, contractors will install the granite caps on the wall that runs north/south and miscellaneous pavers.

The construction is targeted to move to the north side of the Plaza on or about 9/14/2011.  Temporary directional signage will be posted at that time.

No comments:

Post a Comment