Thursday, January 12, 2012

Weekly Construction Update: 1/12/2012

This week the following work is expected to be completed:
  • excavating the pit below future link elevator
  • waterproofing of the pit below link elevator
  • Framing pit below link elevator
  • Pouring the concrete floor of link elevator pit
  • Installation of shut-off valves on riser pipes
  • Installation of columns
  • Begin wiring of fire panel
  • Removal of radiant panels around existing elevator shaft
  • Removal of duct work from existing elevator shaft
Next week the following work is expected:
  • Frame, rebar, and pour walls around future link elevator shaft
  • Continue wiring fire alarm panel
  • Continued abatement of areas around existing elevator shaft

No comments:

Post a Comment