This week the following work is expected to be completed:
- excavating the pit below future link elevator
 
- waterproofing of the pit below link elevator
 
- Framing pit below link elevator
 
- Pouring the concrete floor of link elevator pit
 
- Installation of shut-off valves on riser pipes
 
- Installation of columns
 
- Begin wiring of fire panel
 
- Removal of radiant panels around existing elevator shaft
 
- Removal of duct work from existing elevator shaft
 
Next week the following work is expected:
- Frame, rebar, and pour walls around future link elevator shaft
 
- Continue wiring fire alarm panel
 
- Continued abatement of areas around existing elevator shaft
 
 