| Preparing for steel tie-in for link |
| Plumbing riser replacement work in office building restrooms |
| Plumbing riser replacement work |
| Demo of old plaza wall between Cathedral and office building. Using jack hammer with safety precautions. |
| Pouring concrete floor in lower level |
| leveling concrete floor in lower level |
| Working on concrete floor in lower level of office building |
| Delivery of concrete for lower level floor |
| progress on elevator pit and beginning shaft walls |
| New plumbing in lower level kitchen/laundry room area |
| New plumbing in lower level kitchen/laundry room area |
| Framing installation continues for walls in lower level |
| Delivery central! |
| CMU (concrete block) delivery |
| Deliveries in the site of the future link and welcome center |
| New wall construction at site of old cooling tower |
| Electrician at work bending conduit |