Wednesday, March 28, 2012

Weekly Construction Update: 3/28/2012

This week the following work is expected:
  • Continuing to erect steel and decking for the link structure
  • Building concrete block wall
  • Roughing in of the drain on the roof
  • Building walls around the stairs in the former lower level ramp area
  • Prepping and pour stairs in the former lower level ramp area
  • Laying out and beginning to set pavers on the upper tier of the north plaza
  • Continued work on the water feature (ground level of the north plaza) including forming the structure and roughing in the electricity
Next week the following work is expected:
  • Finishing roughing in the drain on the roof of the link structure
  • Roof and skylight blocking
  • Framing in the link structure
  • Finishing upper stairs in the former lower level ramp area
  • Beginning to prep lower stairs in the former lower level ramp area
  • Setting pavers on the upper tier of the north plaza
  • Electric work on the upper tier of the north plaza
  • Installing rebar, embeds, and placing water feature on the ground level of the north plaza
  • Demoing slab concrete to the end of the wall on the ground level of the lower plaza