Friday, June 8, 2012

Weekly Construction Update: 6/8/2012

This week the following work is expected:
·         Hanging drywall on the walls and ceilings in the lower level
·         Taping drywall seams in the lower level
·         Tying drains on link structure roof into drainage system
·         Ongoing installation of duct and pipe riser in the office tower
·         Installation of building overhang ceiling on the north plaza
·         Removal of tree on Rush Street to accommodate new water main tie-in
·         Installation of limestone on the east plaza wall (facing Rush Street)

Next week the following work is expected:
·         Continued taping of drywall seams in the lower level
·         Placement of a concrete slab in link/addition structure
·         Ongoing installation of duct and pipe riser in the office tower
·         Installation of building overhang ceiling on the north plaza
·         Tie-in of water main on Rush Street